Assume you are risk-averse and have the following three choices. Which project will you select? Compute the coefficient of variation for each.

Expected Value Standard Deviation

A \(2,200 \)1,400

B 2,730 1,960

C 2,250 1,490

Short Answer

Expert verified

The coefficient of variation for Part A is computed as 0.655, Part B is computed as 0.718 and part C is computed as 0.662.Project A should be selected.

Step by step solution

01

Computation of coefficient of Part A

Coefficientofvariation=StandardDeviationExpectedvalue=1,4402,200=0.655

02

Computation of coefficient of Part B

Coefficientofvariation=StandardDeviationExpectedvalue=1,9602,730=0.718

03

Computation of coefficient of Part C

Coefficientofvariation=StandardDeviationExpectedvalue=1,4902,250=0.662

04

Selection of project

The project A should be chosen as it has the lowest coefficient of variation, less coefficient of variation means the project has relatively less risk than the other projects.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free