Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscar’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

4. What price should Oscar’s managers set for unfinished bookcases to earn a net profit of $19 per bookcase?

Short Answer

Expert verified

Answer

The sales price for unfinished bookcase: $80.93

Step by step solution

01

Cost-based pricing

Cost-based pricing is the process of setting the price based on the full product cost. Under cost-based pricing desired net profit is added to the full product cost to get the sales price. Full product cost includes all the developing, producing, and delivering costs relating to products or services.

02

Computation of sales price for unfinished bookcase

Per unit full product cost for unfinished bookcase: $61.93

Net profit per bookcase: $19

Salesprice=perunitfullproductcost+Netprofitperunit=$61.93+$19=$80.93

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscar’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

2. Suppose that pre-manufacturing activities, such as product design, were assigned to the standard bookcases at \(5 each and to the unfinished bookcases at \)3 each. Similar analyses were conducted of post-manufacturing activities such as distribution, marketing, and customer service. The post-manufacturing costs were \(20 per standard bookcase and \)18 per unfinished bookcase. Compute the full product costs per unit.

Harcourt Pharmaceuticals manufactures an over-the-counter allergy medication. The company sells both large commercial containers of 1,000 capsules to health care facilities and travel packs of 20 capsules to shops in airports, train stations, and hotels. The following information has been developed to determine if an activity-based costing system would be beneficial:

Activity Estimated Estimated Quantity

Indirect Cost Allocation Base of Allocation Base

Materials handling \( 96,000 Number of kilos 24,000 kilos

Packaging 210,000 Number of machine hours 3,000 hours

Quality assurance 114,000 Number of samples 1,900 samples

Total indirect costs \) 420,000

Other production information includes the following:

Commercial Containers Travel Packs

Units produced 2,800 containers 51,000 packs

Weight in kilos 9,800 5,100

Machine hours 1,960 510

Number of samples 560 765

Requirements

3. Use the predetermined overhead allocation rates to compute the activity-based costs per unit of the commercial containers and the travel packs. Round to two decimal places. (Hint: First compute the total activity-based costs allocated to each product line, and then compute the cost per unit.)

Explain how the work cell manufacturing layout increases productivity.

How is the Conversion Costs account used in JIT costing?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free