Question:Blanchette Plant Service completed a special landscaping job for Kerry Company. Blanchette uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Kerry job included \(750 in plants; \)1,300 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Kerry job?

Short Answer

Expert verified

Answer

Total cost of Kerry job: $2,190

Step by step solution

01

Total overhead cost

Designcost=No.ofdesigns×Predeterminedallocationoverheadrate=$1×$290=$290Plantingcost=No.ofplants×Predeterminedallocationoverheadrate=$30×$20=$600Totaloverheadcost=Designcost+Planningcost=$290+$600=$890

02

Total cost of Kerry job

Totalcost=Directlabourcost+Totaloverheadcost=$1,300+$890=$2,190

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free