Turbo Champs Corp. uses activity-based costing to account for its motorcycle manufacturing process. Company managers have identified three supporting manufacturing activities: inspection, machine setup, and machine maintenance. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Inspections \( 5,700 Number of inspections

Machine setup 22,000 Number of setups

Machine maintenance 6,000 Finishing of machine hours

Total \) 33,700

Turbo Champs expects to produce 20 custom-built motorcycles for the year. The motorcycles are expected to require 100 inspections, 40 setups, and 100 machine hours.

Requirements

2. Compute the expected indirect manufacturing cost of each motorcycle.

Short Answer

Expert verified

Indirect cost per motorcycle:$172

Step by step solution

01

Indirect Manufacturing cost

Indirect manufacturing costs are the costs that are not visible in the production process but help the production process to run efficiently. These costs cannot be directly attributed to each product or service but can be allocated based on some allocation base.

02

Calculation of indirect manufacturing cost per bumper

The predetermined overhead allocation rate computed in the earlier part is as follow: –

Inspection: $57

Machine setup: $55

Machine maintenance: $60

The indirect cost for each motorcycle would be the sum of all the allocation rate.

Indireetcostperbumper=inspectionrate+machnesteuprate+Machinemaintenance=$57+$55+$60=$172

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

What is a just-in-time management system?

Question:Refer to Exercises E19-24 and E19-25. Suppose Western’s direct labor rate was $280 per hour. The Halbert engagement used the following resources last month:

Allocation Base Halbert

Direct labor hours 170

Pages 310

Applications used 80

Requirements

1. Compute the cost assigned to the Halbert engagement, using the ABC system.

2. Compute the operating income or loss from the Halbert engagement, using theABC system.

Harris Systems specializes in servers for workgroup, e-commerce, and ERP applications. The company’s original job costing system has two direct cost categories: direct materials and direct labor. Overhead is allocated to jobs at the single rate of \(22 per direct labor hour.

A task force headed by Harris’s CFO recently designed an ABC system with four activities. The ABC system retains the current system’s two direct cost categories. Overhead costs are reflected in the four activities. Pertinent data follow:

___________________________________________________________________

Activity Allocation Base Predetermined Overhead

Allocation Rate____

Materials handling Number of parts \) 0.85

Machine setup Number of setups 500.00

Assembling Number of assembling hours 80.00

Shipping Number of shipments 1,500.00_______

Harris Systems has been awarded two new contracts, which will be produced as Job A and Job B. Budget data relating to the contracts follow:

____________________________________________________________

Job A Job B__

Number of parts 15,000 2,000

Number of setups 6 4

Number of assembling hours 1,500 200

Number of shipments 1 1

Total direct labor hours 8,000 600

Number of units produced 100 10

Direct materials cost \( 220,000 \) 30,000

Direct labor cost \( 160,000 \) 12,000__

Requirements

1. Compute the budgeted product cost per unit for each job, using the original costing system (with two direct cost categories and a single overhead allocation rate).

Question:The Santos Shirt Company manufactures shirts in two departments: Cutting and Sewing. The company allocates manufacturing overhead using a single plantwide rate with direct labor hours as the allocation base. Estimated overhead costs for the year are\(500,000, and estimated direct labor hours are 200,000. In June, the company incurred 17,500 direct labor hours.

1. Compute the predetermined overhead allocation rate.

2. Determine the amount of overhead allocated in June.

The Santos Shirt Company has refined its allocation system by separating manufacturing overhead costs into two cost pools—one for each department. The estimated costs for the Cutting Department are \)200,000. They will be allocated based on directlabor hours, which are estimated to be 125,000 hours for the year. The estimated costs for the Sewing Department are $300,000.Those costs will be allocated based on machine hours, which are estimated to be 150,000 hours for the year. In June, the companyincurred 10,000 direct labor hours in Cutting and 12,500 machine hours in Sewing.

3. Compute the predetermined overhead allocation rates for each department.

4. Determine the total amount of overhead allocated in June.

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscar’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

1. Compute the manufacturing product cost per unit of each type of bookcase.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free