Question:Blanchette Plant Service completed a special landscaping job for Kerry Company. Blanchette uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Kerry job included \(750 in plants; \)1,300 in direct labor; one design; and 30 plants.

Requirements

3. If Blanchette desires an operating income of 30% of cost, how much should the company charge for the Kerry job?

Short Answer

Expert verified

Answer

Sales price: $2,847

Step by step solution

01

Full product cost

Full product cost is the total cost relating to developing, producing, and delivering the product or services. It includes all the pre-production, during-production, and post-production costs.

Full product cost is used to determine the sales price under cost-based pricing.

02

Computation of sales price

Salesprice=Totalcost+(100+costpercent)100=$2,190×130100=$2,847

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question:Blanchette Plant Service completed a special landscaping job for Kerry Company. Blanchette uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Kerry job included \(750 in plants; \)1,300 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Kerry job?

The following information is provided for Orbit Antenna Corp., which manufactures two products: Lo-Gain antennas and Hi-Gain antennas for use in remote areas.

Activity Cost Allocation Base

Setup \( 58,000 Number of setups

Machine maintenance 30,000 Number of machine hours

Total indirect manufacturing costs \) 88,000

Lo-Gain Hi-Gain Total

Direct labor hours 1,200 3,800 5,000

Number of setups 40 40 80

Number of machine hours 3,000 2,000 5,000

Orbit Antenna plans to produce 125 Lo-Gain antennas and 225 Hi-Gain antennas.

Requirements

2. Compute the ABC indirect manufacturing cost per unit for each product.

Willitte Pharmaceuticals manufactures an over-the-counter allergy medication. The company sells both large commercial containers of 1,000 capsules to health care facilities and travel packs of 20 capsules to shops in airports, train stations, and hotels. The following information has been developed to determine if an activity-based costing system would be beneficial:

Activity Estimated Estimated Quantity

Indirect Cost Allocation Base of Allocation Base

Materials handling \( 95,000 Number of kilos 19,000 kilos

Packaging 200,000 Number of machine hours 5,000 hours

Quality assurance 112,500 Number of samples 1,875 samples

Total indirect costs \) 407,500

Actual production information includes the following:

Commercial Containers Travel Packs

Units produced 2,400 containers 50,000 packs

Weight in kilos 9,600 5,000

Machine hours 1,680 500

Number of samples 240 750

Requirements

3. Use the predetermined overhead allocation rates to compute the activity-based costs per unit of the commercial containers and the travel packs. Round to two decimal places. (Hint: First compute the total activity-based costs allocated to each product line, and then compute the cost per unit.)

Darby Corp. is considering the use of activity-based costing. The following information is provided for the production of two product lines:

Activity Cost Allocation Base

Setup \( 105,000 Number of setups

Machine maintenance 60,000 Number of machine hours

Total indirect manufacturing costs \) 165,000

Product A Product B Total

Direct labor hours 7,000 5,000 12,000

Number of setups 30 170 200

Number of machine hours 1,600 2,400 4,000

Darby plans to produce 375 units of Product A and 250 units of Product B. Compute the ABC indirect manufacturing cost per unit for each product.

How is the Conversion Costs account used in JIT costing?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free