Question:Stella, Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Stella’s senior managers expect the engineering work to reduce appraisal, internal failure, and external failure activities. The predicted reductions in activities over the two-year life of the skateboards follow. Also shown are the predetermined overhead allocation rates for each activity.

Activity Predicted Predetermined

Reduction in Overhead Allocation

Activity Units Rate per Unit

Inspection of incoming raw materials 390 \( 44

Inspection of finished goods 390 19

Number of defective units discovered in-house 1,200 50

Number of defective units discovered by customers 325 72

Lost profits due to dissatisfied customers 75 102

Requirements

2. Stella spent \)103,000 on design engineering for the new skateboard. What is the net benefit of this “preventive” quality activity?

Short Answer

Expert verified

Answer

The net benefit of design engineering amounts to $12,620.

Step by step solution

01

Quality improvement activity or programs

Quality improvement activities or programs are the programs that intend to improve quality and reduce costs. There are four types of programs based on quality cost-

1) Prevention cost

2) Appraisal cost

3) Internal failure costs

4) External failure cost

02

Calculation of net benefit of preventive quality activity

Total predicted quality cost savings: $115,620

Amount spent on design engineering: $103,000

Netbenefitofdesignengineering=Totalpredictedqualitycostsavings-amountspentondesignengineering=$115,620-$103,000=$12,620

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Clancy’s Carpet Cleaning Services uses ABC to allocate overhead costs and has computed the following predetermined overhead allocation rates:

Activity Allocation Base Allocation Rate

Supplies Number of square feet \( 0.05 per square foot

Travel Number of customer sites \) 20.00 per site

Clancy cleans the carpets for an apartment management firm. When a renter moves out, the apartment management firm contacts Clancy to clean the carpets in preparation for a new tenant. During the past month, Clancy cleaned the carpets of 23 apartments with 1,200 square feet each. What amount of indirect costs should Clancy allocate to the apartment firm for the month?

Question:High Mountain produces fleece jackets. The company uses JIT costing for its JIT production system.

High Mountain has two inventory accounts: Raw and In-Process Inventory and

Finished Goods Inventory. On April 1, 2018, the account balances were Raw and In-Process Inventory, \(10,000; Finished Goods Inventory, \)2,100.

The standard cost of a jacket is \(33, composed of \)12 direct materials plus \(21

conversion costs. Data for April’s activities follow:

Number of jackets completed 19,000

Number of jackets sold (on account for \)50 each) 18,600

Direct materials purchased (on account) \( 220,500

Conversion costs incurred \) 500,000

Requirements

1. What are the major features of a JIT production system such as that of High Mountain?

2. Prepare summary journal entries for April. Underallocated or overallocated

conversion costs are adjusted to Cost of Goods Sold monthly.

3. Use a T-account to determine the April 30, 2018, balance of Raw and In-ProcessInventory.

Darby Corp. is considering the use of activity-based costing. The following information is provided for the production of two product lines:

Activity Cost Allocation Base

Setup \( 105,000 Number of setups

Machine maintenance 60,000 Number of machine hours

Total indirect manufacturing costs \) 165,000

Product A Product B Total

Direct labor hours 7,000 5,000 12,000

Number of setups 30 170 200

Number of machine hours 1,600 2,400 4,000

Darby plans to produce 375 units of Product A and 250 units of Product B. Compute the ABC indirect manufacturing cost per unit for each product.

Question:Low Range produces fleece jackets. The company uses JIT costing for its JIT production system.

Low Range has two inventory accounts: Raw and In-Process Inventory and

Finished Goods Inventory. On March 1, 2018, the account balances were Raw and In-Process Inventory, \(9,000; Finished Goods Inventory, \)1,700.

The standard cost of a jacket is \(40, composed of \)12 direct materials plus \(28 conversion costs. Data for March’s activities follow:

Number of jackets completed 15,000

Number of jackets sold (on account, for \)50 each) 14,600

Direct materials purchased (on account) \( 177,500

Conversion costs incurred \) 521,000

Requirements

1. What are the major features of a JIT production system such as that of Low Range?

How can ABM be used by service companies?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free