Martin, Inc. manufactures bookcases and uses an activity-based costing system. Martin’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 230,000

Number of parts

\)1.50

Assembly

3,200,000

Number of assembling direct labor hours

16.00

Finishing

150,000

Number of finished units*

3.00

*Refers to the number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Martin produced two styles of bookcases in April: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

3,000

\(54,000

\)67,500

9,000

4,500

Unfinished bookcase

3,500

56,000

52,500

7,000

3,500

Requirements

2. Suppose that pre-manufacturing activities, such as product design, were assigned to the standard bookcases at \(5 each and to the unfinished bookcases at \)3 each. Similar analyses were conducted of post-manufacturing activities such as distribution, marketing, and customer service. The post-manufacturing costs were \(24 per standard bookcase and \)18 per unfinished bookcase. Compute the full product costs per unit.

Short Answer

Expert verified

Full product cost per unit

For standard bookcase: $101

For unfinished bookcase: $71

Step by step solution

01

Step-by-Step-SolutionStep 1: Computation of full product cost for standard bookcase

Manufacturing cost for standard bookcase computed in earlier part: $216,000

Productdesigncost=Costperunit×No.ofunitsproduced=$5×3,000=$15,000

Analysiscost=Costperunit×No.ofunitsproduced=$24×3,000=$72,000

Totalfullproductcost=Manufacturingcost+Productdesigncost+Analysiscost=$216,000+$15,000+$72,000=$303,000

Fullproductcostperunit=TotalfullproductcostNo.ofunitsproduced=$303,0003,000=$101

02

Computation of full product cost for unfinished bookcase

Manufacturing cost for unfinished bookcase computed in earlier part: $175,000

Productdesigncost=Costperunit×No.ofunitsproduced=$3×3,500=$10,500

Analysiscost=Costperunit×No.ofunitsproduced=$18×3,500=$63,000

Totalfullproductcost=Manufacturingcost+Productdesigncost+Analysiscost=$175,000+$10,500+$63,000=$248,500

Fullproductcostperunit=TotalfullproductcostNo.ofunitsproduced=$248,5003,500=$71

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

PetSmart, Inc. is a large specialty pet retailer of services and solutions for the needs of pets. In addition to selling pet food and pet products, PetSmart also offers dog grooming services including bath, nail trim, teeth brushing, aromatherapy to reduce everyday stress, and nail polish and stickers. PetSmart even offers a Top Dog service that includes a premium shampoo, milk bath conditioner, scented cologne spritz, teeth brushing, and bandana or bow.

Assume PetSmart, Inc. expects to incur \(380,000 of indirect costs this year. The company allocates indirect costs based on the following activities:

___________________________________________________________________

Activity Estimated Allocation Base Estimated Quantity

Cost of Allocation

Base____

Admission \) 60,000 Number of admissions 20,000

Cleaning 240,000 Cleaning direct labor hours 100,000

Grooming 80,000 Grooming direct labor hours 4,000

Total indirect costs \( 380,000________________________________________

Requirements.

2. Assume a customer brought in Sophie, a beagle, for Top Dog service. PetSmart used the following resources:

_____________________________________________

Allocation Base Sophie, Beagle

Number of admissions 1

Cleaning direct labor hours 1

Grooming direct labor hours 0.5______

Determine the total cost of the Top Dog service for Sophie assuming the total direct materials cost was \)3.50 and the total direct labor cost was $12 per DLHr.

Explain the difference between the target price and target cost.

List and define the four types of quality costs.

Question:Refer to Exercise E19-24. The president of Western suspects that her allocation of indirect costs could be giving misleading results, so she decides to develop an ABCsystem. She identifies three activities: documentation preparation, information technologysupport, and training. She figures that documentation costs are driven by thenumber of pages, information technology support costs are driven by the number ofsoftware applications used, and training costs are driven by the number of direct laborhours worked. Estimates of the costs and quantities of the allocation bases follow:

Activity

Estimated Cost

Allocation Base

Estimated quantity of allocation base

Documentation Preparation

\( 85,850

Pages

1,317 Pages

Information technology support

150,150

Applications used

715 applications

Training

424,000

Direct labor hours

4,000 hours

Total Indirect costs

\) 640,000

Compute the predetermined overhead allocation rate for each activity. Round to thenearest dollar.

Question:Roxi, Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Roxi’s senior managers expect the engineering work to reduceappraisal, internal failure, and external failure activities. The predicted reductionsin activities over the two-year life of the skateboards follow. Also shown are thepredetermined overhead allocation rates for each activity.


Activity

Predicted Reduction in Activity Units

Predetermined Overhead Allocation Rate per unit

Inspection of incoming raw materials

395

\( 44

Inspection of finished goods

395

26

Number of defective units discovered in-house

1,500

54

Number of defective units discovered by customers

275

73

Lost profits due to dissatisfied customers

100

103

Requirements

1. Calculate the predicted quality cost savings from the design engineering work.

2. Roxi spent \)106,000 on design engineering for the new skateboard. What is the net benefit of this “preventive” quality activity?

3. What major difficulty would Roxi’s managers have in implementing this costs-of quality approach? What alternative approach could they use to measure quality improvement?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free