Martin, Inc. manufactures bookcases and uses an activity-based costing system. Martin’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 230,000

Number of parts

\)1.50

Assembly

3,200,000

Number of assembling direct labor hours

16.00

Finishing

150,000

Number of finished units*

3.00

*Refers to the number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Martin produced two styles of bookcases in April: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

3,000

\(54,000

\)67,500

9,000

4,500

Unfinished bookcase

3,500

56,000

52,500

7,000

3,500

Requirements

4. What price should Martin’s managers set for unfinished bookcases to earn a net profit of $19 per bookcase?

Short Answer

Expert verified

The sales price for unfinished bookcase: $90

Step by step solution

01

Step-by-Step-SolutionStep 1: Cost-based pricing

Cost-based pricing is the process of setting the price based on the full product cost. Under cost-based pricing desired net profit is added to the full product cost to get the sales price. Full product cost includes all the developing, producing, and delivering costs relating to products or services.

02

Computation of sales price for unfinished bookcase

Per unit full product cost for unfinished bookcase: $71

Net profit per bookcase: $19

SalesPrice=Perunitfullproductcost+Netprofitperunit=$71+$19=$90

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Koehler (see Exercise E19-15 and Exercise E19-16) makes handheld calculators in two models—basic and professional—and wants to further refine its costing system by allocating overhead using activity-based costing. The estimated \(721,000 of manufacturing overhead has been divided into three primary activities: Materials Handling, Machine Setup, and Insertion of Parts. The following data have been compiled:

Material Handling

Machine Setup

Insertion of Parts

Total

Overhead costs

\) 45,000

\( 136,000

\) 540,000

$ 721,000

Allocation base

Number of parts

Number of setups

Number of parts

Expected usage:

Basic Model

32 parts per calculator

24 setups per year

32 parts per calculator

Professional

Model

58 parts per calculator

44 setups per year

58 parts per calculator

Requirement 2

Compare your answers for Exercise E19-15, Exercise E19-16, and Exercise E19-17. What conclusions can you draw?

Question:Lally, Inc. produces universal remote controls. Lally uses a JIT costing system. One of the company’s products has a standard direct materials cost of \(9 per unit and a standardconversion cost of \)35 per unit. During January 2018, Lally produced 500 unitsand sold 495 units on account at \(45 each. It purchased \)4,800 of direct materials onaccount and incurred actual conversion costs totaling \(14,000.

Requirements

1. Prepare summary journal entries for January.

2. The January 1, 2018, balance of the Raw and In-Process Inventory account was\)70. Use a T-account to find the January 31 balance.

3. Use a T-account to determine whether conversion costs are overallocated orunderallocated for the month. By how much? Prepare the journal entry to adjustthe Conversion Costs account.

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

1. Compute the total estimated indirect manufacturing cost for 2018.

Darby Corp. is considering the use of activity-based costing. The following information is provided for the production of two product lines:

Activity Cost Allocation Base

Setup \( 105,000 Number of setups

Machine maintenance 60,000 Number of machine hours

Total indirect manufacturing costs \) 165,000

Product A Product B Total

Direct labor hours 7,000 5,000 12,000

Number of setups 30 170 200

Number of machine hours 1,600 2,400 4,000

Darby plans to produce 375 units of Product A and 250 units of Product B. Compute the ABC indirect manufacturing cost per unit for each product.

Clason, Inc. manufactures door panels. Suppose Clason is considering spending the following amounts on a new total quality management (TQM) program:

___________________________________________________________________

Strength-testing one item from each batch of panels \( 68,000

Training employees in TQM 27,000

Training suppliers in TQM 39,000

Identifying suppliers who commit to on-time delivery of

perfect-quality materials 58,000

Clason expects the new program would save costs through the following:

___________________________________________________________________

Avoid lost profits from lost sales due to disappointed customers \) 86,000

Avoid rework and spoilage 63,000

Avoid inspection of raw materials 57,000

Avoid warranty costs 15,000

Requirements

1. Classify each cost as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost.

2. Should Clason implement the new quality program? Give your reason.

Answer

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free