Question:Roxi, Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Roxi’s senior managers expect the engineering work to reduceappraisal, internal failure, and external failure activities. The predicted reductionsin activities over the two-year life of the skateboards follow. Also shown are thepredetermined overhead allocation rates for each activity.


Activity

Predicted Reduction in Activity Units

Predetermined Overhead Allocation Rate per unit

Inspection of incoming raw materials

395

\( 44

Inspection of finished goods

395

26

Number of defective units discovered in-house

1,500

54

Number of defective units discovered by customers

275

73

Lost profits due to dissatisfied customers

100

103

Requirements

1. Calculate the predicted quality cost savings from the design engineering work.

2. Roxi spent \)106,000 on design engineering for the new skateboard. What is the net benefit of this “preventive” quality activity?

3. What major difficulty would Roxi’s managers have in implementing this costs-of quality approach? What alternative approach could they use to measure quality improvement?

Short Answer

Expert verified

Predicted quality cost savings:$115,620

Net Benefit of design engineering:$12,620

Alternative approaches to COQ – Poor quality cost, Total quality cost, Qualified Function Development

Step by step solution

01

Step-by-Step-SolutionStep1: Calculation of predicted quality cost savings

Activity

Predicted reduction in activity units

Allocation rate per unit

Predicted quality cost savings

Inspection of incoming raw material

390

44

$17,160

Inspection of finished goods

390

19

$7,410

Number of defective units discovered in house

1200

50

$60,000

Number of defective units discovered by customers

325

72

$23,400

Lost profits due to dissatisfied customers

75

102

$7,650

Total predicted quality cost savings

$115,620

02

Calculation of net benefit of preventive quality activity

Total predicted quality cost savings: $115,620

Amount spent on design engineering: $103,000

Netbenefitofdesignengineering=Totalpredictedqualitycostsavings-Amountspentondesignengineering=$115,620-$103,000=$12,620

03

Major difficulty in implementing the cost-of-quality approach and its alternatives

The difficulties in implementing the COQ approach are as follows –

1) Measuring the quality cost is the major difficulty as every cost cannot be measured like profit loss due to unhappiness of customers.

2) Another difficulty in implementing this approach is the lack of knowledge of using this approach efficiently.

3) Another difficulty arises due to the lack of needed tools to collect, organize, filter, and report quality costs.

Alternative approaches to COQ

Alternative approaches to COQ are as follows –

1) Poor Quality cost – This is the improved model and ignores the prevention and appraisal costs as they are problematic to measure.

2) Total cost of quality – TCOQ model differs from COQ in the sense that TCOQ does not include maintenance and quality training costs as in the COQ model. Thus it is not a preferred model as that of COQ.

3) Qualified function development – QFD was developed to understand the customer requirements and maximize the quality positively by creating a comprehensive quality system.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Explain how the work cell manufacturing layout increases productivity.

Define value engineering. How is it used to control costs?


Darrel & Co. makes electronic components. Chris Darrel, the president, recently instructed Vice President Jim Bruegger to develop a total quality control program. “If we don’t at least match the quality improvements our competitors are making,” he told Bruegger, “we’ll soon be out of business.” Bruegger began by listing various “costs of quality” that Darrel incurs. The first six items that came to mind were:

a. Costs incurred by Darrel customer representatives traveling to customer sites to repair defective products, \(13,000.

b. Lost profits from lost sales due to reputation for less-than-perfect products, \)35,000.

c. Costs of inspecting components in one of Darrel’s production processes, \(40,000.

d. Salaries of engineers who are redesigning components to withstand electrical overloads, \)65,000.

e. Costs of reworking defective components after discovery by company inspectors, \(50,000.

f. Costs of electronic components returned by customers, \)70,000.

Classify each item as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost. Then determine the total cost of quality by category.

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free