How is the predetermined overhead allocation rate used by service companies?

Short Answer

Expert verified

The service companies use the predetermined overhead allocation rate for allocating the indirect costs to individual jobs by applying it to the actual working hours.

Step by step solution

01

Overheads

Overhead is defined as the total of indirect expenses. It is the expenses which are not convinently identified for any particulars revenue unit.

02

Use of predetermined overhead allocation rate in service companies

The predetermined allocation rate is used by the service company to know the actual overhead expense incurred by the company. It is applied to the actual unit base to compute the actual overhead expense.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

The manufacturing records for Sporty Kayaks at the end of the 2018 fiscal year show the following information about manufacturing overhead:

Overhead allocated to production

\(409,200

Actual manufacturing overhead cost

432,000

Predetermined overhead allocation rate

\)44 per machine hours

Requirements

2. Was manufacturing overhead overallocated or underallocated for the year, and by how much?

Superior Construction, Inc. is a home builder in Arizona. Superior uses a job order costing system in which each house is a job. Because it constructs houses, the company uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the year, it estimated construction overhead of \(1,150,000 and total direct labor costs of \)5,750,000. The following events occurred during August:

a. Purchased materials on account, \(400,000.

b. Requisitioned direct materials and used direct labor in construction. Recorded the materials requisitioned.

Direct material

Direct Labor

House 402

\)58,000

\(44,000

House 403

62,000

32,000

House 404

61,000

58,000

House 405

86,000

57,000

c. The company incurred total wages of \)300,000. Use the data from Item b to assign the wages. Wages are not yet paid.

d. Depreciation of construction equipment, \(6,700.

e. Other overhead costs incurred: Equipment rentals paid in cash, \)30,000; Worker liability insurance expired, \(7,000.

f. Allocated overhead to jobs.

g. Houses completed: 402, 404.

h. House sold on account: 404 for \)250,000.

Requirements

1. Calculate Superior’s predetermined overhead allocation rate for the year.

2. Prepare journal entries to record the events in the general journal.

3. Open T-accounts for Work-in-Process Inventory and Finished Goods Inventory.

Post the appropriate entries to these accounts, identifying each entry by letter.

Determine the ending account balances, assuming that the beginning balances

were zero.

4. Add the costs of the unfinished houses, and show that this total amount equals the ending balance in the Work-in-Process Inventory account.

5. Add the costs of the completed house that has not yet been sold, and show that this equals the ending balance in Finished Goods Inventory.

6. Compute gross profit on the house that was sold. What costs must gross profit

cover for Superior Construction?

Following is a list of cost system characteristics and sample companies. Match each to either job order costing or process costing.

h. A company that bottles milk into one-gallon containers.

June production generated the following activity in Bentley Chassis Company’s Work-in-Process Inventory account:

June 1 balance

\(36,000

Direct materials used

32,000

Direct labor assigned to jobs

40,000

Manufacturing overhead allocated to jobs

28,000

Additionally, Bentley Chassis has completed Jobs 142 and 143, with total costs of

\)37,000 and $48,000, respectively.

Requirements

4. What is the gross profit on Job 143?

Why would the manager of a service company need to use job order costing?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free