Question: P18-9 (LO5,6) EXCEL (Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost \(600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at \)900,000. The following data pertain to the construction period.

2017

2018

2019

Cost to date

\(270,000

\)450,000

$610,000

Estimated cost to Complete

330,000

150,000

-

Progress billing to date

270,000

550,000

900,000

Cash collected to date

240,000

500,000

900,000

Instructions

Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.

Short Answer

Expert verified

Answer

Gross profit for each year:

2017:$135,000

2018:$90,000

2019:$65,000

Step by step solution

01

Definition of Percentage of Completion Method

The method of recognizing the revenue and gross profit for a contract is the percentage of the complete method. This method calculates the percentage of work completed based on the cost incurred to recognize the revenue and profit.

02

Calculation of gross profit under the percentage of completion method

2017

2018

2019

Contract price

$900,000

$900,000

$900,000

Less:

Estimated total cost

($600,000)

($600,000)

($610,000)

Estimated total gross profit

$300,000

$300,000

$290,000

Gross profit Recognized:

Particular

2017

2018

2019

Gross profit for each year

$135,000

$225,000

$290,000

Less: Profit recognized in the previous year

($0)

($135,000)

($225,000)

Gross profit

$135,000

$90,000

$65,000

Working note:

Calculation of estimated total cost:

2017

2018

2019

Cost to date

$270,000

$450,000

$610,000

Add: Estimated cost to complete

330,000

150,000

0

Estimated total cost

$600,000

$600,000

$610,000

The formula for calculating gross profit:

Grossprofit=costtodateestimatedcost×Estimatedgrossprofit-Grossprofitrecognizedinpreviousyear

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Destin Company signs a contract to manufacture a new 3D printer for \(80,000. The contract includes installation which costs \)4,000 and a maintenance agreement over the life of the printer at a cost of $10,000. The printer cannot be operated without the installation. Destin Company as well as other companies could provide the installation and maintenance agreement. What are Destin Company’s performance obligations in this contract?

When must multiple performance obligations in a revenue arrangement be accounted for separately?

What is the transaction price? What additional factors related to the transaction price must be considered in determining the transaction price?

(Gross Profit on Uncompleted Contract) On April 1, 2017, Dougherty Inc. entered into a cost plus fixed fee contract to construct an electric generator for Altom Corporation. At the contract date, Dougherty estimated that it would take 2 years to complete the project at a cost of \(2,000,000. The fixed fee stipulated in the contract is \)450,000. Dougherty appropriately accounts for this contract under the percentage-of-completion method. During 2017, Dougherty incurred costs of \(800,000 related to the project. The estimated cost at December 31, 2017, to complete the contract is \)1,200,000. Altom was billed $600,000 under the contract.

Instructions

Prepare a schedule to compute the amount of gross profit to be recognized by Dougherty under the contract for the year ended December 31, 2017. Show supporting computations in good form.

Tyler Financial Services performs bookkeeping and tax-reporting services to startup companies in the Oconomowoc area. On January 1, 2017, Tyler entered into a 3-year service contract with Walleye Tech. Walleye promises to pay \(10,000 at the beginning of each year, which at contract inception is the standalone selling price for these services. At the end of the second year, the contract is modified and the fee for the third year of services is reduced to \)8,000. In addition, Walleye agrees to pay an additional $20,000 at the beginning of the third year to cover the contract for 3 additional years (i.e., 4 years remain after the modification). The extended contract services are similar to those provided in the first 2 years of the contract.

Instructions

(a) Prepare the journal entries for Tyler in 2017 and 2018 related to this service contract.

(b) Prepare the journal entries for Tyler in 2019 related to the modified service contract, assuming a prospective approach.

(c) Repeat the requirements for part (b), assuming Tyler and Walleye agree on a revised set of services (fewer bookkeeping services but more tax services) in the extended contract period and the modification results in a separate performance obligation.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free