Get started for freeWhich characteristics must a project have for critical path scheduling to be applicable? What types of projects have been subjected to critical path analysis?
Assuming an 80 percent learning rate, if the 4th unit takes 100 hours to produce, the 16th unit should take how long to produce?
Schedule the following activities using CPM:
Activity | Immediate Predecessor | Time (Weeks) |
A | _ | 1 |
B | A | 4 |
C | A | 3 |
D | B | 2 |
E | C,D | 5 |
F | D | 2 |
G | F | 2 |
H | E,G | 3 |
Designing products for aesthetics and with the user in mind is generally called what?
What do you think might be some barriers to the successful, effective use of the project management software packages discussed in the chapter?