For the network shown:

a. Determine the critical path and the early completion time in weeks for the project.

b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.

Short Answer

Expert verified

The project ending explains how the project aim was met successfully. It encompasses the project's last stages, which include acceptance of item, an analysis of the results, quality verification, as well as project closure settlement.

Step by step solution

01

(a) Critical Path

The critical path is found by determining the longest period of dependent tasks as well as calculating the time it takes to accomplish tasks from beginning to end. The most essential activities, as well as events that are structured into a dependency order and also have a direct influence on the project’s finishing timeline, are represented by the critical path.

02

Explanation

Critical path = Path taking maximum duration.

Critical path = A-B-D-G

03

(b) For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule

Early completion time of project = Time taken by the critical path activities= 25 weeks.

The table is shown below:

Determine the slope for each activity:

Slope = (Crash cost – Normal cost) / (Normal time – Crash time)

Cost incurred = $3000

Duration of the project = 23-1

= 22 weeks.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free