Chapter 4: Q21OQ. (page 583)
The MRP gross requirements for Item X are shown here for the next 10 weeks. The lead time for A is two weeks, and the setup cost is \(9. There is a carrying cost of \)0.02 per unit per week. The beginning inventory is 70 units.
Week | Gross requirement |
1 | 20 |
2 | 10 |
3 | 15 |
4 | 45 |
5 | 10 |
6 | 30 |
7 | 100 |
8 | 20 |
9 | 40 |
10 | 150 |
Use the least total cost or the least unit cost lot-sizing method to determine when and for what quantity the first order should be released.
Short Answer
20 unitsshould be ordered to cover the needs for the periods in the least-cost method.