Question: What priority rule do you use in scheduling your study time for midterm examinations? How many alternative schedules exist if you have 5 exams to study for?

Short Answer

Expert verified

Answer

The priority rule will be either FCFS or SOT

The alternatives available to students are 120

Step by step solution

01

Priority rule used during examination for scheduling

The first exam will get more study time, so the First come, first served scheduling method can be used. An alternative way is to use SOT. The exam with the least preparation time will get more study time before the exam.

02

Calculate the alternatives

If there are five exams, then the number of alternatives in five is factorial. That is. After each exam, one alternative is chosen, leaving the student with one less alternative, which goes on till the last exam. This is why the five factorial is applied.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

This is the total amount required for a particular item

Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent stock-outs at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, \(100 for each temp; layoff, \)200 for each worker laid off; inventory holding, \(5 per unit-quarter; backorder, \)10 per unit; straight time, \(5 per hour; over time, \)8 per hour. Assume that the productivity is 0.5 units per worker hour, with eight hours per day and 60 days per season.

In a service setting, what general operations–related variable is not available compared to a production setting?

Given the following history, use a three-quarter moving average to forecast the demand for the third quarter of this year. Note, the 1st quarter is Jan, Feb, and Mar; 2nd quarter Apr, May, Jun; 3rd quarter Jul, Aug, Sep; and 4th quarter Oct, Nov, Dec.

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Last year

100

125

135

175

185

200

150

140

130

200

225

250

This year

125

135

135

190

200

190

Planning orders using a lot-for-lot (L4L) technique is commonly done because it is simple and intuitive. It also helps to minimize holding costs as you are only ordering what is needed when it is needed. So far it sounds like a good idea. Are there any disadvantages to this approach?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free